Elevated Flare Systems for Burn Pit Replacements

Elevated Flare Systems for Burn Pit Replacements March 2015 - In September 2013, Escher Process Modules (Escher) was awarded a contract from Petroserv Limited for the (EPIC) delivery of eight flare systems to Qatar Petroleum – for “mitigation of burn pits in Dukhan Project”. The flares will replace the eight burn pits of the Dukhan gas fields of Qatar Petroleum. 

Currently, the main flare components are manufactured in the Netherlands and shipped to Qatar. The local production of the flare stacks started December 2014. The installation followed by commissioning and start-up of the first flare systems is planned for mid-March 2015. By the end of 2015, all the burn pits will be replaced.

Click here to read more about this article.